George Washington Memorial Parkway Roadway Construction Project - GWMP 934(1) Minnehaha Creek Pedestrian Bridge (Glen Echo)
Description:
The project consists of stabilization of the erosion under the Minnehaha Creek Pedestrian Bridge that connects the Clara Barton National Historic Site Parking Area with Glen Echo Park. Work includes stabilizing the stream bank of the upstream approach to the northern bridge pier to prevent further erosion, protecting the footing of the bridge pier from further erosion and scour, and repairing the bridge pier. Other miscellaneous work includes removing boulders from within the stream to help redirect the stream away from the eroding bank and bridge pier.
Traffic Control / Affects to Public:
The pedestrian bridge will be open to pedestrian traffic at all times. The available walkway widths may be reduced to allow for equipment and material access to the work site. Other potential affects to the public include the closure of portions of the parking area to allow the Contractor access to the work site as well as equipment and material storage.
Design/Construction Schedule:
This project was awarded on June 2007, and is currently under construction. Construction is expected to be completed in November 2007.
George Washington Memorial Parkway Roadway Construction Project - GWMP 1A101 - Pimmit Run
Description:
The project consists of stabilization of the erosion under the GWMP Bridge over Pimmit Run. Repairs include stabilizing the stream bank of the upstream approach to the northern bridge pier to prevent further erosion, protecting the footing of the bridge pier from further erosion and scour, and providing river training techniques, a process to influence the stream channel to migrate away from the eroding stream bank. Other miscellaneous work includes erosion repairs under the bridge caused by the deck drainage scuppers.
Traffic Control / Affects to Public:
The GWMP Bridge over Pimmit Run will be open to traffic at all times. Lane closures may be necessary for equipment and material access to the work site. No lane closures will occur during the standard GWMP Rush Hours of 5:30 am to 10:00 am and 3:00 pm to 7:00 pm, Monday through Friday. Other potential affects to the public include the closure of the foot trails under the bridge along Pimmit Run. Portions of the Fort Marcy and/or Turkey Run Parking Areas can be expected to close to allow the Contractor access to the work site as well as equipment and material storage.
Design/Construction Schedule:
This project is currently under design and tentatively scheduled for award in Fall of 2007. Construction is expected to begin in Winter 2007/Spring 2008.
George Washington Memorial Parkway Roadway Construction Project - GWMP 4(1),5(1) - Spout Run
Description:
The project consists of stabilization of the scour and erosion damage at the arch bridge/culverts under eastbound (near the Washington Turn-Around) and westbound (near the GWMP) Spout Run Parkway over Spout Run. Repairs for both structures include repairing the undermining and scour of the abutments and footings, stabilizing the erosion along the abutments, wingwalls, and stream banks, replacing deteriorated and missing vertical expansion joint filler, and cleaning exposed rebar and coating with epoxy. Other miscellaneous work includes removing trees, boulders, and other debris from within the stream to help redirect the stream away from the structures, repair of the stone masonry joints, and removing vegetation as necessary to help prevent damage to the structures.
Traffic Control / Affects to Public:
The Spout Run Parkway will be open to traffic at all times. Lane closures may be necessary for equipment and material access to the work sites. No lane closures will occur during the standard GWMP Rush Hours of 5:30 am to 10:00 am and 3:00 pm to 7:00 pm, Monday through Friday.
Design/Construction Schedule:
This project is currently under design and tentatively scheduled for award Spring of 2009. Construction is expected to begin in Spring/Summer of 2009.
George Washington Memorial Parkway Roadway Construction Project - GWMP 11(2) Memorial Avenue and Memorial Circle from Arlington National Cemetery (ANC) to Arlington Memorial Bridge
Description:
Rehabilitation of Memorial Avenue and Memorial Circle from Arlington National Cemetery (ANC) to Arlington Memorial Bridge. Work includes asphalt pavement reconstruction, milling, asphalt overlay, installation of sanitary sewer pipe, installation of storm drain inlets and pipes, reconstruction of sidewalks and handicap ramps, installation of granite curbs, pavement striping, and other miscellaneous work.
Traffic Control:
The project will be constructed under traffic using lanes closures, except as noted below. The Contractor will not be allowed to work in the road, including transporting material to or from the work site, during rush hours. Rush hours are from 5:30 a.m. to 10:00 a.m., and from 3:00 p.m. to 7:00 p.m., Monday through Friday.
Memorial Avenue will be reconstructed using lanes closures with temporary concrete barriers or drums. At least three (3) lanes of traffic will be maintained at all times from ANC to the Memorial Avenue Bridge.
Memorial Circle will be repaired using single lane closures with drums for the curb, drainage, and sidewalk work. At least two (2) lanes of traffic will be maintained around Memorial Circle at all times, except during one weekend road closure. Pavement resurfacing (milling and overlay) will be performed using a complete closure of Memorial Circle during one weekend. Arlington Memorial Bridge will also be closed at this time. Traffic will be detoured around the work area using existing roads.
Schedule:
This project was awarded in January 2006 and is substantially complete. Final tree planting is expected to be completed in Fall 2007.
George Washington Memorial Parkway Roadway Construction Project - GWMP 1A97
Humpback Bridge
Description:
The project consists of the rehabilitation of the George Washington Memorial Parkway (GWMP) from Interstate 395 to the Columbia Island Marina entrance in Arlington County, Virginia and the District of Columbia. This work will include the replacement of the Humpback Bridge, construction of an acceleration lane, asphalt pavement removal and replacement through the project limits, realignment of portions of the Mount Vernon Trail (multi-use), construction of pedestrian underpasses, and other miscellaneous work.
Additional Information
George Washington Memorial Parkway Roadway Construction Project - GWMP 1A79 Access Ramp to Reagan National Airport
Description:
Bridge widening and deck replacement for GWMP bridge over North Access Ramp to Reagan National Airport. The bridge widening is to provide trail access over the bridge, separated from traffic. Currently, the trail crosses the bridge along the shoulder. Only 4-inch high mountable curb separate pedestrians and traffic. Work will also include painting of steel members and repair to bridge lighting underneath.
Traffic Control:
During Rush Hour 4 - 11 foot lanes will be maintained. The Contractor may not erect traffic control devices for lanes during rush hour without penalty. All advance setting of traffic control devices must be performed outside of rush hour as defined in the contract. Outside of rush hour one-lane traffic each way is allowed. Morning Rush Hour (5:30 AM to 10:00 AM Monday through Friday). Evening Rush Hour (3:00 PM to 7:00 PM Monday through Friday)
Work period:
There are a number of work restrictions concerning traffic for Sundays and particular holidays such as Memorial Day weekend, Independence Day weekend, Labor Day weekend, Thanksgiving Day weekend, Christmas and New Years. Traffic will be open to 4-lanes during these periods.
Schedule:
Project was awarded in August 2005. Final paving and striping expected to be completed in Fall 2007.
George Washington Memorial Parkway Roadway Construction Project - GWMP 100(1),103(1),104(1) - West Boulevard Drive, East Boulevard Drive, and Northdown Road
Description: -
West Boulevard Drive - frontage road for the GWMP, from Alexandria Avenue to Collingwood Road. The proposed work consists of milling and overlay of the asphalt roadway, minimal pavement spot reconstruction, regrading and/or stabilizing shoulders, and lane striping.
-
East Boulevard Drive - frontage road for the GWMP, from Kent Road to the eastern turn before ending in a cul-de-sac. The roadway includes a northern connector road from the GWMP. The proposed work consists of milling and overlay of the asphalt roadway, pavement spot reconstruction, regrading and/or stabilizing shoulders, and lane striping.
-
Northdown Road - frontage road for the GWMP, from the GWMP to Southdown Road. The proposed work consists of milling and overlay of the asphalt roadway, extensive pavement spot reconstruction, regrading and/or stabilizing shoulders, and lane striping. The stone paved waterway will be repaired at specific locations.
Traffic Control / Affects to Public:
The three roadways will be open to traffic at all times. Lane closures will be necessary with the use of flaggers directing traffic. All construction activities will be performed Monday through Friday from 8:00 am to 5:00 pm. No construction activities will occur on weekends, holidays, or during the night. Construction activities will comply with all noise ordnance laws set by Fairfax County.
Design/Construction
Schedule:
This project is currently under design and tentatively scheduled for award in 2011. Construction is expected to begin in Spring/Summer of 2011.
|