Much like people, every road, every highway, has its own personality...its own character


Skip Navigation Links.

Eastern Federal Lands Highway Division
703-404-6260
1-800-892-8776
Prompt #3: Construction Information

Email:
efl.fhwa@dot.gov
Subject reference: Construction Information

Printer Friendly Version
Colonial Parkway (Colonial National Historical Park) - VA COLO 2011-1(1)

Colonial Parkway - COLO 2011-1(1)

Bridge embankment stabilization at College Creek, Mill Creek and Isthmus Bridges Project

Traffic Sign

This section will be updated on a weekly basis.

Construction Updates

Traffic Control/Weekend and Night Work

  • Project is substantially complete

Traffic Control

  • No additional lane closures are expected

General Project Description

Project work involves stabilization of flood damaged bridge embankments. The work includes placing riprap along the embankments and bridge abutments for the College Creek, Mill Creek, and Isthmus Bridges, and other miscellaneous work.

Design/Construction Schedule:

This project was awarded on July 2, 2013. Construction began on September 9, 2013. Expected completion is mid-November 2013.