Williamsburg, Jamestown (Colonial National Historical Park)

Image of a Colonial National Historic Parkway Bridge typical of the Parkway spans over tidal marsh areas.  A concrete structure with low railings blending in with the surroundings and allowing unimpeded views

Williamsburg, Jamestown (Colonial National Historical Park)

Rehabilitation of 27 Bridges and Overlay/Rehabilitation of Several NPS Routes

Traffic Sign

This section will be updated on a weekly basis.

Construction Updates

Work for July 23 through July 30, 2011

  • All project work is complete

Traffic Control/Weekend and Night Work

  • Weekdays & Saturdays: none
  • Weekend: none
  • Night Work: none
Further Details

General Project Description

Project work involves the rehabilitation of Cheatham Annex Access Road (NPS Route 107 A&B), Queen’s Lake Access (NPS Route 108 A&B), Parkway Drive Access Road (NPS Route 109 A&B), and State Route Interchange Ramps 111 A-D with patching in isolated areas with 3inch SACP and overlay with 1 ½ inch SACP, and the rehabilitation of 27 Bridges and 1 tunnel:

  • Beaverdam Creek Bridge
  • Crawford Road Bridge
  • US Route 17 Tour Road Bridge
  • Yorktown Creek Bridge
  • US Route 17 Parkway Bridge
  • Old Williamsburg Road Bridge
  • North Pier Naval Access Road Bridge
  • Mine Depot Overpass
  • Indian Field Creek Bridge
  • Felgate's Creek Bridge
  • Kings Creek Bridge
  • Penniman Road Bridge
  • Hubbard's Lane Bridge (Queen’s Lake Bridge)
  • Parkway Drive Bridge
  • Page Street Bridge
  • Lafayette Street Bridge
  • Newport Avenue Bridge
  • Halfway Creek Bridge
  • College Creek Bridge
  • Mill Creek Bridge
  • Powhatan Creek Bridge
  • Isthmus Bridge
  • Blacks Point Bridge
  • Travis Graveyard Bridge
  • Long Bridge
  • Williamsburg Tunnel
  • C&O Railroad Bridge
  • Wormley Pond Bridge
Traffic Control / Affects to Public:

See Above.

Design/Construction Schedule:

This project was awarded on May 19, 2009. Construction began on June 30, 2009. Expected completion is June 2011.