Ohio Drive near the Lincoln Memorial -- PRA-NAMA 11(4)

District Of Columbia
Rehabilitation of Ohio Drive and Old Constitution Avenue
|
This section will be updated on a weekly basis. The project was substantially complete on December 3, 2010. However, there are a few items of corrective work that will be performed in June 2011. Construction UpdatesWork for July 30, to August 6, 2011
Traffic Control/Weekend and Night Work
Further Details |
General Project Description
The project consists of the rehabilitation of Ohio Drive from Independence Avenue and 23rd Street to Old Constitution Avenue and the resurfacing of Old Constitution Avenue. The work on Ohio Drive includes pavement reconstruction, curb and sidewalk replacements, and Superpave asphalt concrete pavement. The work on Old Constitution Avenue includes asphalt pavement milling, selective full-depth patching, and Superpave asphalt concrete pavement overlay. Both roadways include drainage improvements and other miscellaneous work.
Design/Construction Schedule:
This project was awarded on January 21, 2010. Construction is expected to begin April 25, 2010. The project was substantially completed on December 3, 2010.