Steel-backed Timber
Guardrail Unit Price Analysis (Metric)
| Item No. |
Item Description |
Unit |
Project |
Eng.Est Total |
State |
Date |
Quantity |
Low Bidder |
Low No. 2 |
Low No. 3 |
Low No. 4 |
Low No. 5 |
| 61701G |
Guardrail system SBTA |
m |
BW 1D16,E13,F15 |
15,900,450.00 |
MD |
06/09/92 |
335.3 |
137.80 |
131.23 |
141.08 |
147.64 |
147.64 |
| 61701G |
Guardrail system SBTA |
m |
SUIT 1BC13 |
15,300,000.00 |
MD |
09/01/90 |
2,331.7 |
131.23 |
131.23 |
131.23 |
131.23 |
131.23 |
| 61701G |
Guardrail system SBTA |
m |
GWMP 1A61 |
5,088,750.00 |
VA |
09/17/92 |
1,717.5 |
127.95 |
134.51 |
134.51 |
122.54 |
98.43 |
| 61701G |
Guardrail system SBTA |
m |
PNS 1(1), SCH B |
276,875.00 |
MD |
10/26/93 |
115.8 |
164.04 |
180.45 |
183.73 |
187.01 |
226.38 |
| 61701H |
Guardrail system SBTB |
m |
CUGA 25E24 |
320,000.00 |
KY |
03/28/91 |
112.8 |
141.99 |
0.00 |
0.00 |
0.00 |
0.00 |
| 61701H |
Guardrail system SBTB |
m |
PRA-COLO 1A15,1B31 |
2,522,652.26 |
VA |
05/25/93 |
2,837.7 |
139.60 |
123.03 |
129.13 |
134.51 |
131.23 |
| 61701H |
Guardrail system SBTB |
m |
NPS-PRWI 10(1) |
187,174.95 |
VA |
05/25/94 |
30.5 |
295.28 |
492.13 |
475.72 |
39,370.08 |
0.00 |
| 61701H |
Guardrail system SBTB |
m |
FOOT 8G12 |
1,250,000.00 |
TN |
06/13/91 |
2,002.5 |
104.99 |
0.00 |
0.00 |
0.00 |
0.00 |
| 61701H |
Guardrail system SBTB |
m |
PRA-GWMP 100A26 |
365,447.00 |
MD |
06/14/94 |
97.5 |
164.04 |
150.43 |
147.64 |
0.00 |
0.00 |
| 61701H |
Guardrail system SBTB |
m |
PRA-GWMP 100A26 |
502,192.50 |
MD |
06/14/94 |
97.5 |
164.04 |
150.43 |
147.64 |
0.00 |
0.00 |
| 61701H |
Guardrail system SBTB |
m |
FOOT 8G13,H7 |
3,770,000.00 |
TN |
06/30/92 |
2,804.2 |
120.57 |
0.00 |
0.00 |
0.00 |
0.00 |
| 61701H |
Guardrail system SBTB |
m |
BLRI 2L10,P11 |
625,000.00 |
NC |
07/09/91 |
106.7 |
157.48 |
164.04 |
131.23 |
95.14 |
0.00 |
| 61701H |
Guardrail system SBTB |
m |
DEWA 14(1) |
1,000,000.00 |
PA |
08/25/92 |
140.2 |
196.85 |
196.85 |
213.25 |
0.00 |
0.00 |
| 61701H |
Guardrail system SBTB |
m |
BLRI 2K11 |
870,000.00 |
NC |
08/27/92 |
161.5 |
164.04 |
196.85 |
131.23 |
0.00 |
0.00 |
| 61701H |
Guardrail system SBTB |
m |
INDU 215(1) |
1,825,000.00 |
IN |
09/01/90 |
445.0 |
85.30 |
180.45 |
0.00 |
0.00 |
0.00 |
| 61701H |
Guardrail system SBTB |
m |
BLRI 1S12, T13 |
2,250,000.00 |
VA |
09/01/90 |
283.5 |
129.59 |
137.80 |
170.60 |
0.00 |
0.00 |
| 61701H |
Guardrail system SBTB |
m |
CUGA 25E4 |
69,000,000.00 |
KY |
09/14/90 |
3,352.8 |
232.94 |
177.17 |
177.17 |
82.02 |
147.64 |
| 61701H |
Guardrail system SBTB |
m |
HAFE 14-1(3) |
95,000.00 |
WV |
09/14/91 |
103.6 |
219.06 |
0.00 |
0.00 |
0.00 |
0.00 |
| 61702F |
Terminal section, type FAT-30 |
Each |
SUIT 1BC13 |
15,300,000.00 |
MD |
09/01/90 |
14.0 |
410.00 |
400.00 |
410.00 |
410.00 |
670.00 |
| 61702F |
Terminal section, type FAT-30 |
Each |
CUGA 25E4 |
69,000,000.00 |
KY |
09/14/90 |
8.0 |
71.00 |
1,500.00 |
500.00 |
500.00 |
3500.00 |
| 61702F |
Terminal section, type FAT-30 |
Each |
BW 1F16,G14,H14, |
14,200,000.00 |
MD |
09/16/92 |
1.0 |
35.00 |
900.00 |
720.00 |
1,000.00 |
750.00 |
| 61702F |
Terminal section, type FAT-30 |
Each |
NATR 3X3 |
5,524,000.00 |
MS |
09/20/91 |
2.0 |
575.00 |
550.00 |
300.00 |
0.00 |
0.00 |
| 61702H |
Terminal section, type SBT-BAT |
Each |
SUIT 1BC13 |
15,300,000.00 |
MD |
09/01/90 |
4.0 |
410.00 |
400.00 |
410.00 |
410.00 |
560.00 |
| 61702H |
Terminal section, type SBT-BAT |
Each |
CUGA 25E4 |
69,000,000.00 |
KY |
09/14/90 |
2.0 |
71.00 |
2,000.00 |
800.00 |
500.00 |
6,000.00 |
| 61702Z |
Terminal section, type FAT 20, FAT-30 or
SBT-BAT |
Each |
PRA-COLO 1A15,1B31 |
2,522,652.26 |
VA |
05/25/93 |
58 |
431.25 |
275.00 |
398.94 |
415.00 |
400.00 |
|  |